The recast Energy Performance of Buildings Directive makes the carbon footprint of a whole building part of its energy performance certificate. That calculation runs on product data, and an Environmental Product Declaration is how a panel supplies it.

6 min readUpdated Oct 22, 2026

In short

  • From 1 January 2028, new buildings over 1 000 m² must show their life-cycle carbon footprint on the energy performance certificate, and from 2030 every new building must.
  • That calculation, to EN 15978, runs on product data, and an Environmental Product Declaration to EN 15804+A2 is how a panel supplies it.
  • Rushil has two registered EPDs — thin decorative HPL from 0.55 to 1.8 mm and compact HPL from 2 mm — both valid until 29 June 2031.
Construction site with several tower cranes beside new buildings on a waterfront in Amsterdam
New buildings going up in Amsterdam. From 2028, larger new buildings in the EU have to disclose their life-cycle carbon footprint.Photo: Fons Heijnsbroek · CC0 · Wikimedia Commons · resizedIllustrative photograph from an open archive — not a Rushil product or project.

How this guide was put together

This guide is based on Directive (EU) 2024/1275, the recast Energy Performance of Buildings Directive, and its Annex III on calculating life-cycle global warming potential, together with the European standards it names, and on Rushil's published environmental documentation and the register of the International EPD System, where its declarations are listed. It explains the rules. It makes no claim that any product has a low or reduced environmental impact.

Carbon goes on the certificate

Article 7 of the directive requires Member States to make sure that the life-cycle global warming potential, or GWP, of new buildings is calculated and disclosed in the building's energy performance certificate: from 1 January 2028 for new buildings with a useful floor area of more than 1,000 m², and from 1 January 2030 for all new buildings. By 1 January 2027, each Member State must publish a roadmap for introducing limit values on the total life-cycle GWP of new buildings, with targets from 2030.

The same article makes new buildings owned by public bodies zero-emission buildings from 1 January 2028, and all new buildings from 1 January 2030. Disclosure comes first; limit values are on the way.

How the number is calculated

Annex III sets the method. Life-cycle GWP is reported for each life-cycle stage in kilograms of CO₂ equivalent per square metre of useful floor area, over a reference study period of 50 years, calculated to EN 15978. The building elements in scope follow indicator 1.2 of Level(s), the EU's common framework for sustainable buildings, and national tools may be used where they meet its minimum criteria.

Most importantly for suppliers, the annex says that data for specific construction products calculated under the Construction Products Regulation shall be used when available. Where a façade or interior panel comes with its own verified life-cycle data, the building calculation can use it; where it does not, the calculation has to fall back on generic data.

1 Jan 2028
life-cycle GWP on the certificate of new buildings over 1,000 m²
EU 2024/1275
1 Jan 2030
the same for all new buildings
EU 2024/1275
1 Jan 2027
national roadmaps for life-cycle GWP limit values
EU 2024/1275
50 years
reference study period of the building calculation
EU 2024/1275
2 EPDs
thin and compact HPL, EN 15804+A2, International EPD System
Rushil
2031
both Rushil EPDs valid until 29 June 2031
Rushil
Whole-life carbon and EPDs in six numbers.Diagram drawn for this site from the figures in the article

What an EPD contains

An Environmental Product Declaration is a third-party-verified report of a product's environmental performance over its life cycle, prepared to ISO 14025 and, for construction products, to EN 15804. It is published by a programme operator under product category rules. Under the current version, EN 15804+A2, it reports the product stage, modules A1 to A3, and normally also the end-of-life stage, C1 to C4, and module D, which describes benefits and loads beyond the product's life. Those modules are the building blocks of the EN 15978 calculation the directive asks for.

Rushil's two EPDs

Rushil has two EPDs registered with the International EPD System, both to EN 15804+A2 under the product category rules for construction products, PCR 2019:14, version 2.0.1. One covers thin decorative HPL from 0.55 to 1.8 mm, registration EPD-IES-0032917:001; the other covers compact HPL of 2 mm and above, EPD-IES-0032915:001, cradle to gate with module A5, modules C1 to C4 and module D. Both declare 1 m² of laminate made in Gujarat as a production-weighted average for the product group, carry a version date of 30 June 2026 and are valid until 29 June 2031.

An EPD is not a claim of low impact, and this article makes none. What it gives an architect, a façade consultant or a contractor is product-specific, verified data for KLADS façades, compact cubicles and worktops, and decorative HPL finishes, ready to enter the building's life-cycle calculation.

What this means for façade and interior specifications

From 2028 the life-cycle GWP of larger new buildings becomes part of the project file, and from 2030 that of every new building. Ask for EPDs at the specification stage, and check that they follow EN 15804+A2, that the declared unit and thickness range match the product you specify, and that they are still valid. For Rushil's laminates both declarations run to 2031, and the sustainability document on the downloads page lists them.

Common questions

When does life-cycle GWP have to be disclosed?

Under Article 7 of Directive (EU) 2024/1275, in the energy performance certificate: from 1 January 2028 for new buildings with more than 1,000 m² of useful floor area, and from 1 January 2030 for all new buildings.

Does an EPD mean a product is low-carbon?

No. An EPD reports verified life-cycle data and makes no claim of low or reduced impact. Its value is that the building's calculation can use product-specific figures instead of generic data.

Which Rushil products have an EPD?

Thin decorative HPL from 0.55 to 1.8 mm (EPD-IES-0032917:001) and compact HPL of 2 mm and above (EPD-IES-0032915:001), both to EN 15804+A2 and valid until 29 June 2031.

Sources

  1. Official Journal of the European Union L series — Directive (EU) 2024/1275 on the energy performance of buildings (recast)May 8, 2024 · en
  2. International EPD System — EPD certificate: Thin High Pressure Decorative Laminate, Rushil Décor (EPD-IES-0032917:001)Jun 30, 2026 · en
  3. International EPD System — EPD certificate: Compact HPL, Rushil Décor (EPD-IES-0032915:001)Jun 30, 2026 · en
  4. Rushil Decor — Sustainability and environment: certifications and EPDsen

Compiled for this site from the publications listed above. Summaries are in our own words, not quotations — read the originals for the full argument.

Technical data is based on manufacturer documentation and applicable test reports. Product specifications may vary by grade, thickness, décor, manufacturing batch or application. Please request the latest technical documentation before final specification or installation.